During March we have constructed another 4no. JRF110 BT chambers on either side of the newly constructed concrete bridge deck to complete the BT network diversion to accommodate the HS2 construction works in the area.

Since our last update in December works at Crimscote Solar Farm near Stratford Upon Avon is progressing well.

Works at one of our primary substation builds at Graven Hill in Bicester is taking shape quickly.

Lydon Contracting have been appointed to undertake the civil engineering and construction works to bring in the power supply to facilitate the installation of a 49.9MW solar and storage farm, known as Crimscote Solar Farm near Stratford Upon Avon.

During October phase 1 of the Stansted North 7.5 km 33kV and pilot cable installation commenced using our drum trailers for part of the install and our Beavertail lorry fitted out with a special A Frame for the remainder.

The construction of primary substation compounds is one of Lydon Contracting’s specialist service offerings. Our site in Sheffield has its challenges with access, with it being on a newly constructed commercial development.